1.
|
2.
|
Click Add Stage Row (). Stages organize workflow tasks and approvals. Add tasks and approvals under stages.
|
|
Click Add Task Row () to add the workflow and people tasks you need.
|
|
Click Add Approval Row () to add the approval tasks you need.
|
|
When you move a row, Marketing Operations does not change its task dependencies.
|
|
|
Select Enforce Dependencies to make sure users update only the task after all previous steps are completed.
|
|
|
Set the date as Anchored. Anchored dates cannot move, even if a previous step is late.
|
|
|
Set the time that the work will Schedule Through. By default, Marketing Operations only schedules work on business days. You can calculate schedules to include weekends, holidays, or all calender days.
|
7.
|
Copyright IBM Corporation 2014. All Rights Reserved.
|