To run the Overdue Milestone report
The Overdue Milestone report shows all overdue milestones with task end dates that fall between the selected start and end dates. You can filter the report by using the
Report Start Date
and
Report End Date
parameters as well as the
Task Status
and
Project Status
parameters.
1.
Select
Analytics > Operational Analytics
.
2.
In the list of reports, click
Overdue Milestone Report
.
A screen appears allowing you to set filter criteria.
3.
Choose start and end dates for the report.
4.
Optionally, set filters for Task and Project status.
5.
Click
Finish
to create the report.
The report displays a list of milestones, grouped by the milestone owner, sorted by project code, and containing the following columns: Milestone Owner, Project Code, Milestone, Task Number, Status, Task Name, End Date, Forecast/Actual End, Days Late, and
Notes
.