To calculate date dependencies above a locked task
If a workflow has a locked task, and you change the date of a task that is located above that task, you receive a warning when you calculate date dependencies.
To clarify this task, the procedure that follows assumes:
Task 1.8 is locked.
You need to change the duration of task 1.5 from five days to 10 days.
All tasks are dependent on the previous task.
1.
Open the workflow for editing, and change the duration on task 1.5 from five days to 10 days.
2.
Click the
Date Dependency Calculation
icon (
) next to the end date of task 1.5.
The system displays a warning message, saying you cannot recalculate through the locked row.
3.
Click the start date of task 1.8
4.
Click the
Date Dependency Calculation
icon.
The system calculates the dates below the locked task.