When in edit mode, click the measuring bar for a task and enter a new % Complete number. The measuring bar expands to display a comparable level. For approval tasks, this field is read-only.
|
|||||||||
Forecast/Actual Start
|
For tasks in the pending state, this field represents the Forecast Start date. Forecast Start dates are in italicized font. After you change a task from Pending to Active, this field represents the Actual Start date. Actual Start dates are in regular font.
|
||||||||
Forecast/End
|
For tasks in the pending state, this field represents the Forecast End date. Forecast End dates are in italicized font. After you change a task from Active to Finished, this field represents the Actual End date. Actual End dates are in regular font.
|
||||||||
Forecast/Dur.
|
If you enter both start and end dates, the system automatically calculates a value for this field (the Forecast/End date minus the Forecast/Actual Start date).
|
||||||||
To specify anchored dates for a task, click the column, then select Anchored from the menu. The task date cannot move even if the dates of the tasks it is dependent on change.
|
|||||||||
|
|||||||||
If a workflow task has a role in its Member Role(s) column, when you assign people to roles, the workflow automatically adds a person in the corresponding Members column.
|
|||||||||
If a workflow task has a role in its Reviewer Role(s) column, when you assign people to roles the workflow automatically adds a person in the corresponding Reviewer column.
|
|||||||||