To calculate date dependencies above a locked task
If a workflow has a locked task, and you change the date of a task that is located above that task, you receive a warning when you calculate date dependencies.
To clarify this task, the procedure that follows assumes:
Task 1.8 is locked.
You need to change the duration of task 1.5 from 5 days to 10 days.
All tasks are dependent on the previous task.
1.
Open the workflow for editing, and change the duration on task 1.5 from 5 days to 10 days.
2.
Click the Date Dependency Calculation icon (
) next to the end date of task 1.5.
The system displays a warning message, saying you cannot recalculate through the locked row.
3.
Click the start date of task 1.8
4.
Click the Date Dependency Calculation icon (
).
The system calculates the dates below the locked task.