To edit program or project metrics
When you created your program or project using the wizard, you entered various metrics on the Tracking page. To edit the values you entered, follow the procedure below.
If the program is linked to a plan, or the project is linked to a program, you must finalize the edits you made before they will roll up to the parent object.
This procedure describes editing metrics for a program; editing metrics for a project is similar.
1.
Navigate to the Tracking tab of the program whose metrics you would like to edit.
2.
Click the Program Metrics icon (Page with pencil image).
The Edit Program Tracking page appears.
3.
4.
Click Save and Finish.
The Tracking tab for the program displays. The updated metrics appear in the Program Metrics table.