To link an existing project to a program
Before you can link an existing project to a program, there must be existing projects in your system and you must have the appropriate permission.
After you create a program, you can link existing projects to the program. When you link a project to a program, all the team members listed in both the project and the program receive an email message informing them of the link.
1.
Navigate to the Summary tab of the program that you want to link to an existing project.
2.
Click the Manage Linked Objects icon (Page with pencil and chain links image) and select Link Existing.
A dialog box appears for you to specify the projects to link.
3.
Enter search criteria in the Find by name or codefield.
4.
Click Find.
*
The Search Results field displays only projects that you can link to the program. Only projects with the same budget granularity and security policy as the program will are available. Programs with a status of Canceled, Deleted, or Completed never appear in Search Results.
5.
In the Search Results field, select the projects to link.
6.
Click >> and << to move projects into or out of the Selected Items to Link list box.
7.
Click Save Changes to create child links to the projects you selected.
The projects you added appear in the list of projects at the bottom of the Summary tab of the program.
Security considerations for linking projects and programs