Approval dates
When you create an approval from a workflow task, note the following behavior concerning the Forecast/Actual and Target dates for the approval.
*
If the task contains a date in either the Target End Date or Forecast/Actual End Date field, the system automatically copies the date into the Target Due Date for the approval.
*
If you modify the date in the Target Due Date field, the Forecast/Actual End Date in the corresponding workflow approval task is updated with the new date.
Note the following about the way IBM® Marketing Operations calculates duration when the project owner enters the start and end dates for an approval from a workflow task.
*
*
*
*
*
The Forecast/Actual Duration field in the workflow is overwritten with the sum of approver durations if the duration for an approver is changed and saved.
*
Marketing Operations automatically calculates the approval start date if the Forecast/Actual duration and Forecast/Actual end date are changed.