Managing stage and task sequence
If you change the number for a task or stage, the task is inserted before the row that matches the new number.
For example, assume the stage order as shown here.
1.
2.
3.
4.
5.
If you edit task 5, Marketing Review, changing its number to 3, the new order is as follows.
1.
2.
3.
4.
5.
Now suppose that you edit task 2, Collateral Design, changing its number to 4. The new order is the following.
1.
2.
3.
4.
5.
To move a task or stage to the end, give it any number higher than the final task or stage. For example, to move stage 2, Marketing Review to the end, change its number to 6 or higher.