Configuring the workflow
Click Edit... to configure the workflow. Then, use the toolbar to add and delete stages and tasks. You can also move stages and tasks, manage dependencies, and access other options. After you configure the workflow, you can save it as a workflow template. You can reuse a workflow template in another project template as-is or import and edit it.
1.
2.
Click Add Stage Row (Page with columns and plus sign image). Stages organize workflow tasks and approvals. Add tasks and approvals under stages.
3.
By default, tasks are added in series: each task is dependent on the task that precedes it. To use a different dependency option, click Page with plus sign image and make a selection before you add the next task to the workflow.
*
*
*
Each task that you add uses the same dependency option until you change the selection.
You can also change the dependencies for a task manually: click the task name and supply a comma-separated list of task numbers in parentheses. For more information, see
4.
*
Click Add Task Row (Page with clipboard and plus sign image) to add the workflow and people tasks you need.
*
Click Add Approval Row (Page with thumbs up and plus sign image) to add the approval tasks you need.
You can copy and paste rows. You can also fill, or copy, information from one row to the rows above and below to improve efficiency. Click Gears image for these options.
*
5.
*
When you move a row, Marketing Operations does not change its task dependencies.
6.
You can configure the rows in the following ways:
*
*
Mark tasks and approvals Required. Users cannot skip, rename, or delete rows that are Required.
*
Select Enforce Dependencies to make sure users update only the task after all previous steps are completed.
*
Select a Milestone type. For more information, see Customize milestone types.
*
Set the date as Anchored. Anchored dates cannot move, even if a previous step is late.
*
Set time durations for the Default Duration and Target Effort of the work.
*
Set the time that the work will Schedule Through. By default, Marketing Operations only schedules work on business days. You can calculate schedules to include weekends, holidays, or all calender days.
7.