The task owner or owners. At the task level, project members are referred to as task owners.
That is, in the workflow spreadsheet, you use the Members column to add people to a task; this column refers to project members. When you open the task in the Post Task Update screen, these members are listed as Owners (which refers to task owners).
|
|
Forecast /Actual date and time fields
|
The Forecast/Actual begin and end dates and times for the task. You can edit either or both of the date and time selectors to update the information.
|
A flag to determine whether the task can contain attachments. This field is visible to project owners only. Check the box to allow the task to contain attachments.
|
|
Make sure that you close the dialog box by clicking either Save and Return or Cancel; if you do not use one of the buttons to close the dialog box, the task can remain locked, and no one else can edit it.
|
|
To change the state of a finished task back to active, you must set both the Status to Pending, and the % Complete field to an integer less than 100. If you do not change both fields, after you close the dialog box, the task is still marked as completed.
|
|
|||||||
Copyright IBM Corporation 2012. All Rights Reserved.
|