Post task update dialog box
This dialog appears when you click a workflow task in view mode. Use this dialog as a quick alternative to editing the entire workflow, when you need to update a single task only. From this dialog, you can update certain items, add task attachments, and add comments to the revision history of the project.
The Post Task Update dialog box contains two tabs, Status and Attachments.
Status
The Status tab contains the following fields.
The task owner or owners. At the task level, project members are referred to as task owners.
That is, in the workflow spreadsheet, you use the Members column to add people to a task; this column refers to project members. When you open the task in the Post Task Update screen, these members are listed as Owners (which refers to task owners).
Forecast /Actual date and time fields
The Forecast/Actual begin and end dates and times for the task. You can edit either or both of the date and time selectors to update the information.
A flag to determine whether the task can contain attachments. This field is visible to project owners only. Check the box to allow the task to contain attachments.
*
Make sure that you close the dialog box by clicking either Save and Return or Cancel; if you do not use one of the buttons to close the dialog box, the task can remain locked, and no one else can edit it.
*
To change the state of a finished task back to active, you must set both the Status to Pending, and the % Complete field to an integer less than 100. If you do not change both fields, after you close the dialog box, the task is still marked as completed.
Attachments
The Attachments tab contains the following fields.
*
File: Contains a link to the attachment file and describes the file type and size.
*
Description: Contains revision history and description for the attachment.
*
Actions: Contains links for deleting the attachment or for sending the attachment by email.